Board Building Oversight Committee Meeting Minutes May 19, 2021

District Mission: The Sioux City Community School District exists to educate students to believe in their talents and skills, achieve academic excellence, and succeed in reaching their potential.

The Building Oversight Committee meeting was held on May 19th at 4:00 p.m. with the following topics discussed.

Tim Paul gave an update on the following sales tax projects for FY/21 and FY/22.

  • FY/21 East Middle Athletic Field is in progress and will be complete by the end of June 2021.
  • FY/22 East Middle fire alarm project will begin as soon as school is out for the year and will be completed by August 13th.
  • FY/22 North High sports complex parking lot project will begin the middle of July. The anticipated completion time will be in September.
  • FY/22 O&M roofing project is complete.
  • FY/22 East Middle Roofing project is to start in June with completion by August 13th.

Matt Basye with FEH gave an update and virtual tour of the new Hunt Elementary School. The design is centered on the theme of Arts with a theater and black box room for performances. It has many visual displays in the building that bring part of the old building together with the new.

There was a discussion on future projects including the possible new Sunnyside/Nodland Elementary.

The topic of future meetings will be held at a minimum of two per year.